Source: City of Broken Arrow
Construction of a new landmark gracing the south Broken Arrow skyline is now complete.
“I’m excited to announce that the new $12.5 million elevated water storage tank at New Orleans and Lynn Lane is now online, providing 2.5 million gallons of water to our South Broken Arrow customers when they need it,” Utilities Director Timothy Robins said. “This major infrastructure investment will serve Broken Arrow residents for generations.”
The nearly 200-foot composite facility has a large metal bowl on top and a resilient concrete tower structure below. Its height benefits water pressure through gravity.
“This tank will aid in stabilizing pressures immediately and provide storage volume well into the future,” Robins said.
Water began flowing into the new tank on Nov. 17 as part of a coordinated two-day effort between the technicians at the tank and at the Verdigris River Water Treatment Plant in east Broken Arrow.
The technicians began filling the tank in the evening while the water usage throughout the city was at its lowest so that it wouldn’t negatively impact water pressure for residents. Robins describes it as a “very delicate process” balancing all the water levels in all seven of the City’s water storage tanks around the city.
After filling the tank, the water was tested by the Oklahoma Department of Environmental Quality for several days and passed all inspections before it was approved for public consumption.
The Broken Arrow Municipal Authority awarded the construction contract to Landmark Structures on Oct. 15, 2024, and the project started in early 2025.
Watch Utilities Director Timothy Robins discuss the new elevated water storage tank in New Water Tower Online in Broken Arrow.