By John Dobberstein, Editor
A Tulsa-based developer has sued the city of Broken Arrow, alleging the city is using water service to a proposed subdivision as a “bargaining chip” to resolve a dispute with a Wagoner County rural water district that services part of Broken Arrow.
Blue Chip Land Co. and Executive Homes filed the lawsuit in Tulsa County District Court this month alleging they spent “millions of dollars” building a water system for The Grove 1 to the city’s specifications after the city promised to supply water.
Blue Chip Land Co. is an affiliate of Executive Homes and that develops raw land into buildable lots for homes to be constructed by Executive Homes.
After the Broken Arrow City Council approved a conditional final plat for the 33-acre project, the companies allege the city refused to release the final plat for printing and signing, “because it claims there is uncertainty over which entity will supply water to The Grove I.”
Wagoner County Rural Water District #4, located on the far east side of Broken Arrow, provides water to residents in certain parts of Wagoner County. The Grove I is proposed south of 131st Street and west of County Line Road and appears to fall outside of RWD #4’s coverage map.
Minutes from the city’s approval of the preliminary plat state, “water and sewer are available from the City of Broken Arrow.”
The companies said, “there is no uncertainty” about the water supply because the city has been committed to it for more than 2 years, “and it has no discretion under applicable law to refuse to release the final plat.”
The Grove I is the first phase of a planned single-family community, with 103 lots and three reserve areas. Blue Chip Land Co. said The Grove I and subsequent phases, “will be one of Broken Arrow’s premier neighborhoods with high-quality amenities exceeding those of any subdivision currently constructed in Oklahoma.”
According to the lawsuit, a 2024 staff report for the Broken Arrow Planning Commission to consider stated water service is available from the city. In January, the city reviewed waterline plans for The Grove I and approved them, the lawsuit alleges.
The companies said the city is self-certified to permit water lines of 12 inches and smaller under its subdivision code. Attorneys for the company said the city issued an “at-risk” waterline construction permit that allowed Plaintiffs to begin building the water lines before the Department of Environmental Quality (ODEQ) issued its final permit.
In February the city signed and sent to ODEQ an application for a permit under its own name to construct the water lines for The Grove I as part of the city’s public water supply system, which was approved by ODEQ.
The companies said they designed and built public improvements after relying on the approvals and the city’s direction. The companies noted they have paid the city’s plan-review, permit and inspection fees.
Blue Chip submitted the conditional final plat of The Grove I to the City in July, which they allege states the city “or its successors as the provider” would be responsible for maintain public water mains.
The Planning Commission and City Council approved the conditional final plat this summer, and the companies said there were no conditions or checklist items imposed pursuant to the City Council’s approval of the conditional final plat relating to what entity would provide water service to the subdivision.
“Indeed, the plat makes it clear that the City will provide water service to The Grove I,” the attorneys said.
In October, the companies said, engineers submitted a final plat addressing the city planning staff’s comments about the project, and the city’s Engineering Section manager wrote “construction needs the issue with [the rural water district] finalized on who is supplying water” and that “[w]e may not be able to release the plat if there is no water to the lots.”
According to the lawsuit, the city’s Planning and Development manager wrote, “I understand that it is not clear which agency will be supplying water to the subdivision. Until that is resolved, we will not be able to approve the final plat.”
Until the final plat is released, the city also will not issue building permits for lots or authorize water taps for the lots.
The companies said the only reason the city has given for withholding approval is its dispute with the rural water district, which they are not party to, and the dispute, “has no bearing on the city’s release of the final plat” for the development.”
Attorneys said the city is trying to “negotiate away its rights to provide water service to The Grove I in exchange for the right to provide water service to a different large parcel within the rural water district’s service area.”
Attorneys said the companies have suffered carrying costs, lost opportunity costs, increased construction costs and other harms. And there are some homebuyers who have already paid deposits for lots in The Grove I who can’t get their homes started, putting the contracts at risk.
The companies are asking a district judge to grant a temporary injunction against the city prohibiting city staff from withholding the final plat. They are also seeking payment of monetary damages and repayment of other costs and fees. As of Wednesday the city has not issued any statements about the lawsuit or filed an answered in Tulsa County District Court, and no further court dates have been set.